  • Winter 2013 PSU 5-year capital plan approved – Ag Engineering Building included
  • June 2014 – Programming completed
  • Fall 2014 – Project out for integrated project delivery (IPD) team proposal solicitations
  • January 2015 – IPD team selection finalized
  • Spring 2015 - Spring 2016 -- design
  • Summer 2016 - ABE department relocation
  • Summer 2016 - December 2017 -- construction
  • December 2017 – Completion anticipated
  • December 2017 – ABE department move-in